1-6 Maisonettes:

– Installation of external thermal insulation system.
– Application of protective waterproofing layer at the lower sections.
– Completion of wall chasing and installation of concealed electrical and plumbing pipework.
– Sealing of wall chases with cement-based repair mortar in preparation for interior finishing works.
– Ongoing initial installation works for internal electrical, plumbing, and ventilation

7-9 Maisonettes:

– Execution of preparatory works and reinforcement for ground floor slab casting.

 

Attached below are progress photos taken throughout April:

 


Front exterior of 1-6 mizonets in early, mid and late April

 

  
Interior photos of 1-6 misonnettes

 


Ground floor of 7-9 misonnettes