General site works:
– Electrical power, cold water, and sewage connections completed for the entire complex.

1-6 Maisonettes:
– Internal electrical installation works completed.
– Cement screed poured as sub-base for future floor tiling.

7-9 Maisonettes:
– Completion of slab casting above the first floor level, forming the structural base for the second floor.
– Brick masonry works completed at the lower ground and ground floor levels.

Attached below are progress photos taken after June:

 

Back & front exterior of 1-6 mizonets 

 

 

Interior photos of 1-6 misonnettes at the beginning of July

 

 

Roof of 1-6 mizonets

 

 

Side & front exterior of 7-9 mizonets