General site works:
– Pavement construction completed.
– Infrastructure laid for future fibre-optic connections.
1-6 Maisonettes:
– Floor tiling works in progress.
– Partial installation of balcony doors leading to terraces.
– Partial painting of the building’s exterior.
7-9 Maisonettes:
– Structural frame of the building fully completed
Below will be attached photos of the progress made during July.