General site works:
– Paving works in front of the buildings completed.
– Swimming pool tiling completed.
1-6 Maisonettes:
– Installation of electrical fittings in progress (switches, sockets, and lighting points).
– Installation of sliding balcony doors completed.
– Installation of internal doors completed.
7-9 Maisonettes:
– Brick masonry works completed.
– Plastering works in progress.
– Electrical conduit installation in progres.
Below will be attached photos of the progress made during September.