Construction Progress Report – January 2025

1-6 Maisonettes:

– Second floor columns and roof slab completed.
– Lower ground floor plastering finished.
– First-floor brickwork completed.

7-9 Maisonettes:

– The foundation have been completed.
– The columns of the lower ground floor have been completed.

Attached below are progress photos taken during January.

         