General site works:
– Paving works in front of the buildings in progress.
1-6 Maisonettes:
– Installation of electrical fittings in progress (switches, sockets, and lighting points).
– Installation of sliding balcony doors in progress.
– Floor tiling works progressing.
7-9 Maisonettes:
– Structural frame fully completed.
– Brick masonry works in progress across multiple levels