1-6 Maisonettes:

– Completed plastering.
– Completed bricklaying.

7-9 Maisonettes:

– Poured concrete floor slabs for lower ground floor.
– Poured concrete floor slabs for the underground parking.
– Cast columns for the ground floor.

 

Attached below are progress photos taken 24/08/2025:


Exterior photos of 1-6 misonettes

 

 

 
Interior photos of 1-6 misonettes.

 


7-9 misonettes, ground floor